A general description of the primary work elements is listed below for reference. Contractor is responsible for reviewing all drawing and specifications to obtain a complete understanding of the entire scope of work. The contract includes all work indicated in the contract documents including but not limited to:
1. Mobilization, establishment of site perimeter fence and protection of existing conditions.
2. Selective demolition and removals within the pool filter room and chase walls.
3. Delivery, installation, and assembly onto the premises of any equipment or apparatus
furnished.
4. Swimming pool piping systems for the recirculation and filtration systems and all
swimming pool chemical treatment systems.
5. Swimming pool equipment systems.
6. Surge tank construction.
7. Swimming pool automatic water make-up systems and controls.
8. Equipment and co2 room ventilation system.
9. Reinforced concrete housekeeping pads (for pumps and filters)
10. Start, test, calibrate, and adjust all pool mechanical, recirculation, and chemical equipment
as well as other supplied pool systems including winterization procedures. Commissioning of all systems including UV.
11. Fiberglass walkways, aluminum ships ladder and fiberglass tread stairs.
12. Stainless steel guard railings.
13. Concrete slab repair.
14. Partitions and interior layout alterations.
15. Provide all necessary permits.
16. Closeout documents including warranties.
NYS OPRHP has established the following bid schedule and subsequent work schedule:
- First day of plan sales 21 November 2023
- Pre-Bid Meeting 4 December 2023 (11:00 AM)
- RFI Due Date 11 December 2023 (by 5:00 PM)
- Addendum 01 18 December 2023
- Bid Opening 12 January 2024
- Contract Submittals to OSC 2 February 2024
- Preconstruction Meeting 2 April 2024
- Procure long lead items and store necessary material 2 April 2024 – 9 September 2024
- Mobilization 9 September 2024
- Pool Closure 9 September – 13 December 2024
- Staff Training on or by 6 December 2024
- Substantial Completion 6 December 2024
- Pool Commissioning and Operations 6 December 2024 – 13 December 2024
- Pool Opens to the Public 14 December 2024
- Final Completion 3 January 2024
|